JMG Systems Ltd, Omagh

Project:    JMG Systems Ltd, Omagh
Client:        JMG Systems, Ltd

Works:        Entailed the following:

  • Demolition of existing building to include metal clad roof, steel trusses, steel columns & concrete block infill walls.
  • Construction of new office building attached to existing building. New office comprises structural steel frame on reinforced concrete foundations with external masonry walls cladded with sheet metals, wood paneling & fibre cement panels & precast concrete suspended upper floor. Roof is sheet metal cladding on insulated plywood base. Windows & doors are double glazed aluminium.
  • Internal walls are dry lined metal stud partitions or masonry.
  • Mechanical & electrical services.
  • Construction of retaining walls, paths & new surface to car park.
  • Alterations to the layout of the entrance & car park including removal of existing walls & fences & construction of new.
  • All drainage works.

Duration:    52 Weeks
Stage:        Works complete